Located in the municipalities of Delettes and Enguinegatte in the department of Pas-de-Calais, the wind farm is equipped with five Nordex N100 2.5 MW wind turbines, and was inaugurated on the 5 July 2017. These local authorities chose to make the most of the area’s major natural resource (i.e. the wind) and the tenacity to work on this long-term project for more than 10 years…
TERRE ET LAC CONSEIL’s expertise on this project
Appointed by its client RIVE Private Investment, TERRE ET LAC CONSEIL provided technical and operational assistance on this project during the acquisition phase as well as assistance to the owner during the entire construction period (Sep. 2016 – May 2017). Terre et Lac Conseil has also managed and operated this wind power station since it was commissioned on 20 April 2017